(A) Jog: Jog pump, observe the oil pump rotation is correct, power, anti-oil output and sometimes also likely to have an accident, so remember when operation starts only "jog". Get ready for continuous operation when the pump sound normal and continuous output of oil and other irregularities, and no-load debugging.
(B) no-load debugging: the first l0 20 minutes at low speed, is sometimes necessary to remove the motor and the load of the fuel tank or oil connection. Especially during the cold season, with no load at low speed (warming up) is particularly important, some imported equipment often have strict requirements, some equipped with a heater tank fluid warming. The first trial run be able to run in the low-speed low-voltage action.hydraulic hose fitting
(C) uniform gradually boost acceleration, the specific method of operation is repeatedly tighten and immediately loosen the relief valve, pressure or flow rate of the flow valve to adjust the handle a few times, and pressure gauge observed pressure lifting speed changes and actuators changes in conditions such as heat, vibration and noise of the pump. Found the problem to analyze and solve.
(D) the debug single action combined with electrical machinery in accordance with the action cycle table first, and then transferred to the cycle of action debugging, check each action whether coordination. Generally will be in the process of debugging some problems, such as crawling, impact, and no change to other faults of complex domestic and imported equipment, if there is a difficult problem to solve, can be common consultation, if necessary, resort to hydraulic equipment manufacturers.hydraulic hose assemblies
(E) Finally, enter the full load debugging, the maximum working pressure and the maximum (minimum) speed test the technical performance of hydraulic equipment, check the power, heat, noise and vibration, high-speed impact, low-speed crawling. Check the various parts of the oil spill, the often-load does not leak site increased pressure Shique oil spill. Found the problem immediately removed, and make a written record.
If everything is normal, trial processing specimens. Commissioning is completed, after stopping machine generally want to recover and make a detailed debug log file. Some imported equipment debug log can be used as the basis for the claim.hydraulic ferrule
(F) by applying the above debugging good handle of the hydraulic equipment, and generally do not move. Handwheel on the upcoming packaging factory equipment should release all. Long-term without the equipment, should be the handwheel release the pressure valve to prevent the spring permanent deformation affects the mechanical equipment enabled various types of failures affect performance.