1, pipe installation construction requirements, the ground surface to lay the; reserved for the location of the trench and the
trench clean; windows and doors in place; in place of the radiator; construction site clean up after.
2, pipe prior to installation to cope with the appearance of material and pipe fittings with the working poor, as well as construction
equipment to be checked. Pipe, the pipe surface if any dirt should be promptly cleaned up. Pipes during the installation process should
be strictly prevent the paint, asphalt and other organic matter pollution pipe, the pipe surface.
3, pipe, pipe transport to the site, material handling and storage should be handled with care, arranged in neat rows. Shall be
subjected to sharp hard goods notch, collision, and shall not throw, throw, roll, drag, and sun exposure.
4, pipe, pipe fittings should be stored in room temperature over 40 degrees of the Treasury, the Treasury well-ventilated, shall be
stored with flammable liquids and other dangerous goods with the library.
5, the installation of cleaning agents, such as acetone, alcohol and other flammable materials, transport and storage should be fire
safety, clarification shall be stored in a dry well-ventilated warehouse, when used with the open with, away from sources of ignition.
Million to help up to pb pipe connection
6 should be checked before connecting pipe, pipe end cleaning non-destructive, the fracture is smooth, no glitches.
7, the pipe connection of the ambient temperature is higher than 5 degrees of hot-melt welder should be avoided placed in the outlet, so
as not to affect the connection quality of the welding machine.
Pb piping system connected to the hot melt connection, fused connections and clamping connection in three forms, in the central heating
household metering system is recommended to use hot melt connection.