1, plus a full 46 # hydraulic oil 50kg (preferably a genuine original oil).
2, locators installation: first locator inserted in front of the nose (Note: Locator can be directly inserted into the nose), the other end plugs in the ferrule use for one wire hose electrical control box inside the corresponding socket.
3, connect the power, if you are using a three-phase motor, be careful not to pick inversion (top: a motor fan clockwise direction is forward).
4, after the completion of the above steps, you can turn the wire braided hydraulic hose pressure test.
5, the use of locator: spin down more than a week each pressed into 1mm, every positive spin a grid of 0.01mm, and so on, the same size hose, fittings, metal fittings first reached the required pressure, no longer need to move Locator , has been finished to the specifications of the pressure, the result is fully consistent with data compression, when you complete the first root tubing pressure test, you have learned, and the remaining is gradually skilled.